The Island Water Association, Inc. (IWA) strives to deliver quality water at a reasonable cost. Part of that mission is to improve trouble areas in the system by replacing leaking or failure prone pipes such as the piping system in Shell Harbor.

The Shell Harbor project includes the replacement of about 1,200 linear feet of older piping along with upgrading the valves, fire hydrants, service saddles, service lines, and fittings. The result will be a more reliable system resulting in less inconvenience to our members. For common questions about this project, please see our FAQ Page

A copy of the notification letter sent to all affected members can be found here

A copy of the General Constructions Process can be found here

Click to enlarge image

EVENT SCHEDULE

Event Date
Project Completion 9/15/2017
Scheduled Limpet Drive Outage 8/29/2017 9:00 AM to Noon
Scheduled Paper Fig Court Outage 8/28/2017 Noon to 3:00 PM
Scheduled Golden Olive Drive Outage 8/28/2017 9:00 AM to Noon
Testing completed 8/22/2017
Testing expected completion 8/18/2017
Main water line installation completed 7/28/2017
Mobilization beginning the week of 5/29/2017
Estimated Start Date 5/8/2017
Preliminary design completed, begin permitting 2/27/2017